Dear Ladies and Gentlemen,
as a matter of routine, we would like to provide you with an overview of current and upcoming events within our rail operations. This includes information from the area of the network operator as well as information from the environment of the connected seaport terminals.
- Signal box malfunction in the Edesheim, Leine area from November 19, 2026, at 12:20 a.m. until November 19, 2026, at 1:00 p.m. Result: Widespread rerouting.
- Signal box malfunction due to a water main break in the Northeim area from November 19, 2026, at 2:00 p.m. until approximately November 19, 2026, at 11:00 p.m. Result: longer travel times due to rerouting via the high-speed line. Since long-distance passenger service has priority here, our trains must wait for available time slots before being allowed to enter the high-speed line.
- Point failure on the Hannover-Wülfel line from November 19, 2026, at 10:26 a.m. until November 19, 2026, at 3:00 p.m. Result: extended travel time.
- Signal box malfunction between Hannover-Wülfel <> Kassel and Hannover-Wülfel <> Jühnde from November 19, 2026, at 12:20 a.m. until November 19, 2026, at 10:45 a.m. Consequence: Longer travel times due to rerouting.
- Broken rail in Diepholz from November 18, 2026, until November 19, 2026, at 5:00 p.m. Consequence: Longer travel times
- Traffic diverted due to the major renovation between Hanover and Berlin is placing a massive strain on the infrastructure along the routes we use.
- Dispositive inflow control in Bremerhaven has been in effect since September 3, 2026. Some trains are being denied entry into the Bremerhaven infrastructure.
Due to the circumstances, delays continue to occur at the seaport and inland terminals. These delays have a significant impact on the stability and punctuality of our network. We are making daily efforts to minimize the impact on your bookings as much as possible. Our scheduling department will continue to inform you of any affected bookings on a case-by-case basis. In order to avoid incorrect tours, please check the availability of the loading units before acceptance inland or at the seaport and take our advice notes and order-related information into account.
- Extension of the long-term construction work between Nuremberg, Regensburg, and Passau from February 6, 2026, through December 15, 2026. During this period, there will be two different detours with adjusted train lengths:
- Since September 16 – January 10, 2027 -> 590 m via Salzburg ->22 cars
- Due to the longer distance and increased utilization of the alternative routes, delays are to be expected. Further restrictions cannot yet be fully predicted. We will inform you separately about these. This mainly affects our services to Hungary
For the area of seaport terminals, we would like to point out that your cooperation as a potential terminal customer is also urgently desired.
With regard to deadlines, please refer to our General Terms and Conditions GTC Delivery deadlines or fixed dates cannot be guaranteed. These presuppose unhindered transport conditions on rail and road.